Project Snapshot
Segment: Regulated Energy
Project Type: Pipeline Expansions and LNG
Business Unit: Eastern Shore Natural Gas (Eastern Shore)
Capital Investment: Approximately $80 million
Completed and In-Service: Targeted Q3 2025
Annualized Gross Margin: To be disclosed upon project approval
Primary Location: Worcester County, Maryland
Project Overview
Eastern Shore will invest approximately $80 million to build, own, operate and maintain a five-tank horizontal liquefied natural gas (LNG) storage facility capable of storing up to 0.5 million gallons and providing peak supply of up to 14,000 dts/day. The project includes pipeline looping and additional upgrades. The peak supply will be used by affiliated local distribution companies (LDCs) Chesapeake Utilities – Delaware Division, Chesapeake Utilities-Maryland Division and Sandpiper Energy. Eastern Shore is seeking FERC approval for the project by December 2024.